As We Grow: Construction Updates

On Tuesday, April 4, 2017, the Kearney School District (KSD) community voted to approve a $27 million bond issue. The bond was overwhelmingly approved with an 84% “Yes” vote. KSD wants to sincerely thank the district community for the outpouring of support shown throughout this process.

Since April, the district has been hard at work to further develop plans to move projects forward. This page is dedicated to sharing information about the development and progress made in each area.

Current Updates

Kearney Early Education Center (EEC)
On the inside of the EEC, construction crews started framing, and the two tilt wall panels have been removed from the building on the east side. The estimated construction completion date for the Early Education Center is Spring 2018.

Elementary Schools
Installation of the soft play material for the elementary playgrounds is near completion for both Kearney Elementary and Dogwood Elementary. Southview and Hawthorne Elementary School playgrounds will be completed by the end of Spring 2018.

Middle School
Bid documents for the KMS construction project will be issued on Monday, December 4th. The pre-bid meeting for the KMS project is Thursday, December 7th at 12:30 pm. The bid opening date is set for Monday, December 18th. The estimated construction completion date for the middle school facilities improvements is August 2018.

High School
A pre-bid meeting was held for the KHS construction project on Thursday, November 30. Bids will be opened on December 14 at KHS. The estimated construction completion date for all of the high school is Winter 2018.

KSD is excited to get to work on the newly planned facilities! #AsWeGrow #TeamUpKSD

FOR MORE INFORMATION
Contact
Jeff Morrison
Assistant Superintendent of Human Resources and Student Services
(816) 628-4116
morrisonj@ksdr1.net

© 2016 Kearney School District. All Rights Reserved.